11. Consumables and parent material

Welding consumables are received sealed, stored and handled per the manufacturer’s instructions, and checked against the order with the appropriate certification before use; test certificates are held electronically and in hard copy. Consumables are booked out on the Welding Consumable Issue Record Sheet, with a daily humidity/temperature check by the internal welding coordinator. Unused consumables are returned or, for MMA electrodes, disposed of at shift end; wherever possible MMA consumables are used in vac-packs to avoid drying/re-baking. Special consumables are ordered against a specific job, marked accordingly, and flagged on the technical review.

Parent material, including client-supplied material, is stored so identification is clearly maintained and condition is not adversely affected, per the ISO 9001 system and FPC 01.

Controlled copy. The controlled master of every document in this system is the file held on the IDM server in the welding management system folder structure. This portal is a controlled view of it. Where the two differ, the server file governs.